06/04/2026
Yesterday, subcontractors finished striping and adding street markings around the new mini roundabout at NE 81st Avenue and Halsey Street, the final step before opening the roundabout!
This is part of the NE Halsey Street (80th to 92nd avenues) - Safety and Access to Transit Project, which is working to make it easier and safer for people to walk, bike and roll to and from the NE 82nd Avenue MAX station. NE Halsey Street was among Portland's deadliest corridors for traffic crashes and is now part of the city's High Crash Network.
The contractor has been busy coordinating several subcontractors who have been working at different points along the project. That means some areas may look quiet while crews are focused elsewhere or while a specific subcontractor is scheduled for another day. We’re on track to complete the project later this summer!
In May, Pacific Power energized the new poles, Prairie Electric completed streetlight work, crews did prep work for paving the roundabout and then paved the north half of it, and Nu Wave Concrete formed and poured ADA ramps and traffic islands.
Here’s what’s coming:
• Striping work on NE Jonesmore Street and the NE Halsey and Jonesmore streets intersection in mid- June.
• The underground work for the new rapid‑flashing beacon is complete at NE 88th and Halsey. Next, we’ll be installing the pole and activating the signal.
• Long‑line striping on NE Halsey Street between NE Jonesmore Street and NE 92nd Avenue
• We’ll be microsurfacing to smooth the pavement on the NE Halsey Street bridge over I-84, and installing protective fencing, adding new lane striping, and separating the two-way bike lane.
The total budget for this project is $7.7 million dollars. Sources include a Metro/Federal Regional Flexible Fund grant ($2.4 million), a federal American Rescue Plan Act grant ($2.58 million), a federal earmark grant ($1 million), an additional Metro grant ($900,000), ODOT bridge funds ($412,000), PBOT General Transportation Revenue ($180,000), Fixing Our Streets ($250,000).
Learn more and sign up for project updates at https://www.portland.gov/transportation/pbot-projects/construction/ne-halsey-street-80th-92nd-avenues-safety-and-access