MORE PROGRESS on Hollister Gavilan!!!🥳🥳. Drive by and check it out!!!
🏫 Exciting news about our Measure X Bond! Structural steel er****on is in full swing at our future San Benito Community College – set to wrap up by January 2024. Get ready, as site construction kicks off on December 4, bringing us closer to a state-of-the-art educational hub! 🚧🔧
Join us at our next board meeting on Dec. 12, 2023 for full information, 7:00pm at our Gilroy Campus.
San Benito County Campus Update Dec. 4, 2023
• Structural steel er****on is underway and will be completed in January 2024
• Joint trench work is underway
• Site winterization is being completed
• Site concrete started on Dec. 4th and will be ongoing for the next 3+ months
• Topping out ceremony planned for January SEWER/SEPTIC UPDATE
• Agreement between Sunnyslope Water and the City of Hollister was approved at the Nov. 6th city council meeting
• Next step: City will take the sewer hook up to LAFCO in December
ACCESS IMPROVEMENT PROJECT UPDATE
• Underground storm drain is complete
• PG&E joint trench work is underway
• Curb and gutter concrete work will begin once the joint trench work is completed
PROJECT INFORMATION
• Current Phase: Construction
• Next Milestone: Pour Concrete Footings and SOG
• Total Project Budget: $60.5M
• Anticipated Completion: Fall 2024