Egypt's Minister of Industry Decision No. 171 of 2026 gives delayed industrial projects six to eighteen months to complete, with full penalty relief only for projects at 75% completion or more. Projects that already had an extension get three months, then the land can be withdrawn. Allocated industrial land also cannot be sold, assigned or leased until licensing, registration and operation conditions are met.