18/06/2026
SSR & Co., Advocates & Legal Consultants, successfully represented the National Highway Authority (NHA) in a civil dispute concerning the operation, management and collection of toll revenue under a public procurement contract.
Mr. Saad Javid Satti, Managing Partner of SSR & Co., argued the matter on behalf of NHA and successfully secured the vacation of the ad-interim injunction restraining NHA from encashing the financial guarantees and bid security submitted by the plaintiff.
The learned Court held that the plaintiff had failed to establish a prima facie case, that the balance of convenience did not lie in its favour, and that any alleged loss was ascertainable in monetary terms and therefore did not constitute irreparable loss. Consequently, the application for temporary injunction under Order ###IX Rules 1 and 2 of the Code of Civil Procedure, 1908, was dismissed.
As a result, NHA may now proceed with the encashment of the financial guarantees and take all consequential measures arising from the termination of the contract, in accordance with the applicable contractual and legal framework.